IRRIGATION OF TRADE AND NIKEIA SETTLEMENTS OF THE MUNICIPALITY OF NISYROS
YEAR OF MANUFACTURE: 2020-2023
DESCRIPTION:
The project included the construction of a new water supply network for the transport of drinking water from the island’s desalination facilities to the central storage and distribution tanks of the settlements of Emporio and Nikia, on the arid and difficult island of Nisyros.
Due to the location of the settlements in question at a high altitude, PE100 pipelines, cross section 25 atm and high power pumps were installed. At the same time, construction work took place on the construction of new pump station houses and waterproofing of the existing tanks. Finally, a new telemetry system was installed, for proper communication between the intermediate drinking water transport tanks.